The Developers Plan

Posted on: 6/8/2017

The developers plan to start some enabling work in the grassed area between the School and Heyford Park House.

The footpath between the School and Heyford Park House will be fenced with Heras panels and the site access point near Heyford Park House will be gated and controlled by a banksman when there is construction traffic movement to and from the site.
It will be necessary to access the man hole in the grass area within the school grounds and their intention is to have this fenced whilst work is ongoing.
The construction work will commence on Monday 12 June 2017 and will last for about 4 to 5 weeks.
 